San Mateo has completed targeted sediment removal in Marina Lagoon, removing approximately 1,762 cubic yards as part of a project designed to improve water flow near two creek inlets.

The in-water work is finished and the contractor has left the site, according to the city’s November 2026 project update. Minor site restoration and permit closeout remain, with completion expected before the end of 2026.

The work focused on areas near Leslie Creek and Borel Creek. The original plan included Laurel Creek, but engineering consultant Moffatt & Nichol determined that concentrating the limited dredging at two inlets would be more effective at improving water flow. Dredging near Laurel Creek was reserved for a future larger project.

The City Council awarded the contract to MidCal Dredging, Inc. on May 11, 2026, and the city authorized work to proceed June 3. The city says the in-water work finished within the approved regulatory window.

Larger dredging project remains a separate effort

In its June 2025 update, the city said it was seeking funding for a larger Marina Lagoon dredging project that could remove up to 275,000 cubic yards at an estimated cost exceeding $100 million.

The November update does not provide a new funding status or schedule for that larger effort.

Residents with questions can contact Senior Engineer James Yang at 650-522-7575 or [email protected].